Figure 4-2.-Prime contractor/lead company organization.
Figure 4-3.-Project manager/resource manager organization.
CONCEPTS OF CONSTRUCTION
concepts that are most often used by the Naval
Construction Force (NCF). These concepts are as
Construction operations are conducted under
follows:
several different organizational concepts. Depending
upon the particular objectives of each deployment, the
l
CO and the S-3 officer determine the organizational
l
concept that is most effective for the execution of the
assigned objectives while maintaining readiness
l
Prime contractor/lead company
Project manager/resource manager
Self-sufficient unit/detail
integrity. Although there are many variations that can be
Most construction operations in the NCF are
used in a construction organization, there are three
conducted under the prime contractor/lead company
4-2